Problem Statement
The Australian Government established NBN Co Limited to invest up to $43 billion over eight years delivering superfast broadband nationally. Contractors needed unprecedented transparency and effective real-time reporting across the project lifecycle to maintain control over resources and physical locations.
Scope & Solution
- Developed a bespoke NBN project controls methodology
- Combined industry-leading planning capability with best practice tools
- Developed baseline schedules and progress monitoring across multiple projects
- Resource-loaded schedules using Primavera P6 as input to tender pricing
Outcomes
- Established weekly project schedules and generated progress reports meeting NBN's strict guidelines
- Managed and executed tender schedules for the Tier 1 bid on behalf of John Holland-Conneq JV
- Delivered unprecedented transparency and real-time reporting
Benefits
- Increased control over resources and physical locations for NBN contractors
- Standardised project controls methodology across the programme
- Real-time visibility into project performance and delivery status